Remodeling Process

Your kitchen remodel timeline: before, during, and after demolition

Demolition gets the photos, but ordering and decisions often control the calendar. Here is what happens before the dust and after the cabinets arrive.

Daniel Recio, owner and lead contractor at Home Updates

Daniel Recio

July 27, 2026 12 min read

Completed kitchen remodel showing cabinets, counters, lighting, and appliances in Aurora

The short answer

The schedule starts well before demolition. Settle the layout, appliances, cabinets, long-lead items, permit plan, and temporary kitchen before the crew tears anything out.

Phase 1: scope, measurements, and layout

The team documents the existing room, verifies dimensions, discusses what is staying, and develops the layout. Appliance sizes, cabinet organization, lighting, ventilation, and any wall changes need to be considered together.

This phase is where a homeowner should challenge the plan. Open appliance doors on the drawing, review cabinet elevations, and ask how the room handles groceries, cleanup, cooking, seating, pets, and traffic.

What can move the kitchen timeline

A calendar range is more useful when the assumptions behind it are visible.

Schedule factorFaster pathCommon delay
LayoutFixtures stay near existing locationsStructural or major utility relocation
SelectionsSpecifications approved before orderingLate changes after rough-in or cabinet order
MaterialsLong-lead items arrive before neededBackorders, damage, or incomplete deliveries
InspectionsWork is ready and accessibleCovered work or corrections that affect later trades
CountertopsCabinets installed accurately for templateFabrication starts only after late cabinet fixes

Phase 2: selections and ordering

Cabinets and appliances usually drive the critical dimensions. Countertops, plumbing fixtures, lighting, flooring, backsplash, hardware, and paint follow in a decision schedule.

Materials do not need to arrive in the order they are selected, but the contractor needs confirmed specifications before related rough-ins and orders. A late faucet can affect the sink plan. A changed range can affect power and ventilation.

Phase 3: permits and preconstruction

The permit path depends on the scope. Moving plumbing, changing electrical work, installing new ventilation, or altering structure can require permits and inspections in Aurora.

Before the first day, confirm access, working hours, floor protection, dust barriers, debris route, pet plan, temporary kitchen, material storage, and the primary communication channel.

Phase 4: protection and demolition

The crew isolates the work area, protects the route through the home, disconnects affected systems, and removes the existing finishes included in the scope. Demolition exposes the real framing, plumbing, wiring, and subfloor.

Hidden conditions should be documented with photos and a written recommendation. The homeowner should understand cost and schedule impact before added work moves forward.

Phase 5: framing and rough mechanical work

Walls and openings are adjusted, then plumbing, electrical, and ventilation are placed for the approved plan. These locations need to match the cabinet and appliance documents.

Required rough inspections happen before the work is covered. The schedule should leave those systems accessible until approval.

Phase 6: walls, floors, and cabinets

After approvals, the room moves through insulation where needed, drywall, floor preparation, paint sequencing, and cabinet installation. Cabinet accuracy matters because the countertop is measured from the installed bases.

Walls and floors in older homes are not always perfectly square or level. Skilled installation corrects those conditions so doors align and counters sit properly.

Phase 7: countertop template and finish work

Many stone or engineered-surface counters are templated after cabinets are installed. Fabrication creates a planned gap in the schedule before countertop installation.

Backsplash, plumbing fixtures, appliances, lighting trim, hardware, and final carpentry follow in a coordinated order. Several small trades may appear in a short window.

Phase 8: inspections, punch list, and handoff

The team completes required final inspections, tests fixtures and appliances, adjusts doors and drawers, cleans the room, and walks the project with the homeowner. Remaining details belong on one written punch list with owners and dates.

We give Aurora homeowners the next decision before it becomes the next delay. The calendar works better when nobody is choosing a faucet after the plumber needs its specifications.

Common homeowner questions

Frequently asked questions